Release Checklist: vX.Y.Z
This checklist tracks the process for releasing version vX.Y.Z of the OpenFlexure Microscope Server.
Branching Strategy (as of v3 development)
The current branching strategy is for alpha and beta development of v3. There is an issue open (#606) to discuss branching beyond v3.
- The default branch is called
v3. - Feature branches are made from
v3and merged back intov3. - We do not make a new release branch.
- We still perform a feature freeze before release.
- We still tag each release and post it on the forum.
- We do not rename the
v3branch or create additional long-lived branches for releases.
Phase 1: Preparation (T-6 Weeks minimum)
This phase focuses on planning the release and, crucially, getting any major infrastructure or build system changes merged before the feature freeze.
- **Prepare: **Create the
Server vX.Y.Z/Server vX.Y.Z-(alpha|beta)Amilestone in GitLab at organisation level, and create an issue with this template. - Define Scope: Tag all intended Issues and feature MRs with it. This is often done in a planning meeting with the core team. Issues and MRs should be tagged in:
- Server repo
- Stitching repo
- OS customiser repo
- OFM CLI tools
- Define upstream versions: Does this release depend on a major dependency change (such as new LabThings version)? If so these must have issues.
- Schedule: Set and announce the Feature Freeze and Release Date. Feature freeze should be at least 2 weeks before the release date.
- Feature Freeze - NOT SET
- Release - NOT SET
Phase 2: Feature Freeze And Upstream Releases (T-2 Weeks)
Branching Note: During alpha and beta development, feature freeze marks the point where only bug fixes and release preparation may be merged into the default branch.
- Announce: Announce the Feature Freeze deadline one week out. This should be announced on the OpenFlexure Forum and in a message/email to the core team.
- Deadline: FEATURE FREEZE. All MRs for the milestone must be merged.
- Deadline: UPSTREAM RELEASES. Any of our repos/packages upstream of the OS and server should have a defined release, for this release to target.
- Stitching Released
- Final OS changes merged
- Communication: Inform the team that all new feature work should target the next milestone.
- Final Server Repo Commit: Create a (hopefully) final commit to the server before building the OS with the new version and updated changelog. This commit should include the following:
- Update version string in:
pyproject.tomltest_version_strings.pypackage.jsonpackage-lock.json(in 2 places!)
- Create
CHANGELOGentry- Add a title that is a link to the GitLab compare between the last release tag and this soon-to-be-made tag.
- Add a high level summary of the server changes
- Run changelog helper to generate the list of MRs since the last tag
python change_log_helper.py -b v3 <LAST-TAG-NAME>and copy these in below the summary. - Run
codespellon the changelog and use<!-- codespell:ignore XYZ -->to silence codespell on any spelling errors in MR titles.
- Commit, Push, and Merge
- Update version string in:
Phase 3: Testing & Qualification (T-1 Week)
This phase is dedicated to intensive testing and bug fixing.
- Create Image: Flash at least one SD card with the new image. This image should be created off the default branch.
- Create Release Test Plan: Document the specific tests to be run on top of the default. Add items in section below
- Execute Release Test Plan:
- Add
- items
- here
- Execute Standard Test Plan:
- Camera Calibration
- Picamera v2
- Picamera HQ
- Camera Stage Mapping
- v7 Microscope
- Simulation
- Movement
- v7 Microscope
- Simulation
- Autofocus
- v7 Microscope
- Simulation
- Smart Scan + stitching
- v7 Microscope
- At least 2 different H&E stained slides
- A blue stained biology slide, such as a wheat stem
- Simulation
- v7 Microscope
- Recentre and ROM (v7 Microscope only)
- Opening each tab and sub-tab and checking things look as expected
- v7 Microscope
- Simulation
- Manual
- Camera Calibration
- Capture bugs, Triage and Repeat: Check-off once no more bugs are found in testing.
- Record all bugs found (here and in issues)
- Describe bugs here (#issue-number)
- If needed - Add any showstopper bugs or major regressions to milestone
- Fix these bugs
- Update server changelog!
- Build new image
- Clear testing checklist and this checklist, and start testing again!
- Record all bugs found (here and in issues)
Phase 4: Release Day (T-0)
By this stage:
-
All upstream packages are released.
-
We will release the exact image used for testing.
-
Draft Notes: Draft the release notes for:
- High level summary for the OS release notes
- Combined server and OS summary for the forum
-
Release:
- On
build.openflexure.orgcopy the image that passed testing from/raspbian-openflexure/testing/to/raspbian-openflexure/v3_pre_release/. - OS RELEASE
- Go to the OS Customiser Releases page on GitLab and select New Release
- Create a new Tag Name in the format
vX.Y.ZorvX.Y.Z-(alpha|beta)A - Important! Enter a simple description into the
create tagdialog, or GitLab only creates a lightweight tag.Release for vX.Y.Z-(alpha|beta)Ais minimal and can be used. Check it is targeted at the correct branch, and save the tag. - Copy in the High level summary for the OS into release notes
- Enter the URL to the OS image into the box at the bottom. with "Link Title" as
SD Card Image. - Create the release (This will create the tag)
- SERVER RELEASE
- Go to the Server Releases page on GitLab and select New Release
- Create a new Tag Name in the format
vX.Y.ZorvX.Y.Z-(alpha|beta)A - Important! Enter a simple description into the
create tagdialog, or GitLab only creates a lightweight tag.Release for vX.Y.Z-(alpha|beta)Ais minimal and can be used. Check it is targeted at the correct branch, and save the tag. - Copy in the relevant section from the
CHANGELOG - Enter the URL to the OS image into the box at the bottom. with "Link Title" as
SD Card Image. - Create the release (This will create the tag)
- On
Phase 5: Post-Release
- Communicate: Publish the release announcement on the OpenFlexure forum.
- Announce: Share the forum post on other relevant channels (e.g., LinkedIn, Emailing Collaborators).
- Close: Close this issue and the corresponding GitLab Milestone.
- Celebrate!