Release Checklist: vX.Y.Z

This checklist tracks the process for releasing version vX.Y.Z of the OpenFlexure Microscope Server.


Phase 1: Preparation (T-6 Weeks minimum)

This phase focuses on planning the release and, crucially, getting any major infrastructure or build system changes merged before the feature freeze.

  • Define Scope: Create the vX.Y.Z milestone in GitLab and tag all intended feature MRs with it. Thisn is often done in a planning meeting with the core team.
  • Schedule: Set and announce the Feature Freeze and Release Date. Feature freeze should be at least 2 weeks before the release date.
  • Build System: Identify all required OS-level, build system, or OS customiser changes.
  • Build System: Deadline: All build system MRs must be merged and tested. (This should happen as early as possible in the cycle).

Phase 2: Feature Freeze (T-2 Weeks)

  • Announce: Announce the Feature Freeze deadline one week out. This should be announced on the OpenFlexure Forum and in a message/email to the core team.
  • Deadline: FEATURE FREEZE. All MRs for the milestone must be merged.
  • Branch: Create a release/vX.Y.Z branch from main.
    • From this point, only bug fixes (regressions) are merged into this branch.
  • Communication: Inform the team that all new feature work should target the next milestone.

Phase 3: Testing & Qualification (T-1 Week)

This phase is dedicated to intensive testing and bug fixing on the release/vX.Y.Z branch.

  • Create Image: Flash at least one SD card with the new image.
  • Create Test Plan: Document the specific tests to be run.
  • Execute Test Plan:
    • HQ Camera Test (Optional)
    • High-Resolution Test
    • Low-Resolution Test
    • ROM Test
    • Stitching Tests
    • Test final image on all supported hardware revisions.
    • Test functionality on the Microscope Simulator.
  • Triage: Triage all bugs found. Fix any release-blocking bugs.
  • Repeat: Re-build image and re-test as bugs are fixed. Update release date if absolutely necessary. (Optional)

Phase 4: Release Day (T-0)

  • Final Version Bump:
    • Server Package: Update version number (add specific files).
    • Stitching Package: Update version number (add specific files).
    • Commit and merge the final version bumps into the release/vX.Y.Z branch.
  • Final Build: Generate the final, official release image from the release/vX.Y.Z branch.
  • Draft Notes: Draft the release notes and forum post.
  • Merge: Merge the release/vX.Y.Z branch into main.
  • Tag: Create a new Git tag on main (e.g., vX.Y.Z).
  • Publish:
    • Push the tag to GitLab.
    • Publish new versions of software sub-packages, such as openflexure-stitching, on PyPi.
    • Create a new GitLab Release from the tag.
    • Upload the final release image and other artifacts to the GitLab Release.
    • Paste the release notes into the GitLab Release description.

Phase 5: Post-Release

  • Communicate: Publish the release announcement on the OpenFlexure forum.
  • Announce: Share the forum post on other relevant channels (e.g., LinkedIn, Emailing Collaborators).
  • Close: Close this issue and the corresponding GitLab Milestone.
  • Celebrate!